News Release: from the Katy Freeway Public Information Office


Upcoming Katy Freeway Program Closures

Friday, Sep 26th, 2008

Below is an updated list of the scheduled closures associated with the Katy Freeway Reconstruction Program as of Friday, September 26, 2008.

CONTRACT D (I-10/BELTWAY 8 INTERCHANGE) CLOSURES
. There will be a TOTAL CLOSURE of the I-10/KATY FREEWAY westbound direct connector ramps to BELTWAY 8 north- and southbound from 9 PM, Friday, September 26 until 5 AM, Monday, September 29. Detour to the Kirkwood exit ramp and U-turn to enter the I-10 eastbound mainlanes to access the ramp to Beltway 8 north- and southbound.

. There will be a TOTAL CLOSURE of the BELTWAY 8 southbound frontage road between WESTVIEW and I-10/KATY FREEWAY beginning 6 AM, Saturday, September 27 until 5 AM, Monday, September 29. Detour right on Westview to Brittmoore, turn left to the I-10 westbound frontage road, U-turn at Wilcrest to the I-10 eastbound frontage road, to the Beltway 8 southbound frontage road.

CONTRACTS E1 & E2 (BETWEEN BELTWAY 8 and I-610) CLOSURES
. One outside lane of the I-10/KATY FREEWAY westbound mainlanes between GESSNER and BELTWAY 8 will be closed from 9 PM, Friday, September 26 until 5 AM, Monday, September 29.

. One outside lane of the I-10/KATY FREEWAY eastbound mainlanes between CAMPBELL and CHIMNEY ROCK will be closed on Saturday, September 27 and Sunday, September 28 from 7 AM to 6 PM.

. There will be a TOTAL CLOSURE of the I-10/KATY FREEWAY westbound exit ramp to GESSNER from 9 PM, Friday, September 26 until 5 AM, Monday, September 29. Detour to the Beltway 8 exit and U-turn to the I-10 eastbound frontage road to access Gessner.

. There will be a TOTAL CLOSURE of the I-10/KATY FREEWAY westbound entrance ramp from BLALOCK/ECHO LANE from 9 PM Friday, September 26 until 5 AM, Monday, September 29. Detour to the Beltway 8 entrance ramp.

. There will be a TOTAL CLOSURE of the I-10/KATY FREEWAY westbound entrance ramp from BINGLE/VOSS RD. from 9 PM, Friday, September 26 until 5 AM, Monday, September 29. Detour to the Beltway 8 entrance ramp.

. There will be a TOTAL CLOSURE of the I-10/KATY FREEWAY eastbound exit ramp to BINGLE/VOSS RD. on Saturday, September 27 and Sunday, September 28 from 7 AM to 6 PM. Detour to the Silber exit and U-turn to the I-10 westbound frontage road to Bingle/Voss.

. There will be a TOTAL CLOSURE of the I-10/KATY FREEWAY eastbound exit ramp to CHIMNEY ROCK/WIRT RD. on Saturday, September 27 and Sunday, September 28 from 7 AM to 6 PM. Detour to the Silber exit and U-turn at Silber to the westbound frontage road to Chimney Rock/Wirt.

**************************************************************************************

Please note that all closures are subject to change in the event of inclement weather. For more information on the Katy Freeway Reconstruction Program including up to date information regarding other lane closures along the I-10 corridor, please visit the Katy Freeway website at www.katyfreeway.org or contact the Katy Freeway Public Information Office at 281-589-5924.