Image: Curve Decoration
Image: Katy Freeway Building our Future logo
Image: Reporter and Traffic at night

                                                                                     In the News 

News Release: from the Katy Freeway Public Information Office


Upcoming Katy Freeway Program Closures

Friday, Jan 25th, 2008

Below is an updated list of the scheduled closures associated with the Katy Freeway Reconstruction Program as of Friday, January 25, 2008.

CONTRACT D (I-10/BELTWAY 8 INTERCHANGE) CLOSURES
. There will be a TOTAL CLOSURE of the I-10/KATY FREEWAY westbound frontage road between LUMPKIN and BELTWAY 8 nightly Friday, January 25 and Saturday, January 26 from 9 PM to 5 AM. Traffic will detour right on Lumpkin to Westview, turn left at Westview to the Beltway 8 southbound frontage road to I-10 westbound.

. There will be a TOTAL CLOSURE of the BELTWAY 8 northbound frontage road between I-10/KATY FREEWAY and WESTVIEW Saturday, January 26 and Sunday, January 27 from 5 AM to 5 PM. Traffic will detour to the I-10 eastbound frontage road, turn left at Gessner to Westview, turn left to the to Beltway 8 northbound frontage road.

. There will be a TOTAL CLOSURE of the BELTWAY 8 southbound frontage road between WESTVIEW and I-10/KATY FREEWAY Saturday, January 26 and Sunday, January 27 from 5 AM to 5 PM. Traffic will detour right on Westview to Brittmoore, turn left at Brittmoore to the I-10 westbound frontage road, U-turn at Wilcrest to the I-10 eastbound frontage road to Beltway 8 southbound.

CONTRACTS E1 & E2 (BETWEEN BELTWAY 8 and I-610) CLOSURES

. There will be a TOTAL CLOSURE of the northbound and southbound CHIMNEY ROCK/WIRT RD from 9 PM, Friday, January 25 to 5 AM, Monday, January 28. Northbound traffic will detour to the I-10 eastbound frontage road and u-turn at the signalized intersection at Antoine to the I-10 westbound frontage road to northbound Wirt. Southbound traffic will detour to the I-10 westbound frontage road, u-turn at the signalized intersection at Bingle/Voss Rd to the I-10 eastbound frontage road to Chimney Rock.

. There will be a TOTAL CLOSURE of northbound and southbound SILBER at I-10/KATY FREEWAY on Saturday, January 26 from 4:30 AM to 9 PM. Northbound traffic will detour to the I-10 eastbound frontage road and U-turn at N. Post Oak to the I-10 westbound frontage road to Silber. Southbound traffic will detour to the I-10 westbound frontage road and U-turn through the signalized intersection at Antoine to the I-10 eastbound frontage road to Silber.


***********************************************************************
A Glimpse At Next Weekend’s Work...

CONTRACT C2 (DAIRY ASHFORD to east of KIRKWOOD) CLOSURES
. Left turn access between MEMORIAL and SH-6 will be restricted beginning 10 PM, Friday, February 1 until 5 AM, Monday, February 4 as contractors construct the center portion of the SH-6 lanes. Westbound traffic on Memorial destined to southbound SH-6 will detour right on SH-6 to Grisby, and U-turn to proceed southbound on SH-6. Southbound traffic on SH-6 will detour left on Grisby to Addicks-Howell, right on Addicks-Howeel to Memorial. Law enforcement will be stationed at key locations to facilitate the movement of traffic in the area.

CONTRACTS E1 & E2 (BETWEEN BELTWAY 8 and I-610) CLOSURES

. There will be a TOTAL CLOSURE of northbound and southbound BLALOCK at I-10/KATY FREEWAY beginning 9 PM, Friday, February 1 until 5 AM, Monday, February 4. Northbound traffic will detour to the I-10 eastbound frontage road and U-turn at Campbell to the I-10 westbound frontage road to Blalock. Southbound traffic will detour to the I-10 westbound frontage road and U-turn through the signalized intersection at Bunker Hill to the I-10 eastbound frontage road to Blalock.

. There will be a TOTAL CLOSURE of northbound and southbound ANTOINE at I-10/KATY FREEWAY on Saturday, February 2 from 6 AM to 6 PM. Northbound traffic will detour to the I-10 eastbound frontage road and U-turn at Silber to the I-10 westbound frontage road to Antoine. Southbound traffic will detour to the I-10 westbound frontage road and U-turn through the signalized intersection at Chimney Rock/Wirt Rd to the I-10 eastbound frontage road to Silber.

CONTRACT G (I-610 to west of WASHINGTON) CLOSURES
. There will be a TOTAL CLOSURE of I-10/KATY FREEWAY westbound between WASHINGTON AVE/WESTCOTT ST and I-610/WEST LOOP beginning 9 PM, Friday, February 1 until 5 AM, Monday, February 4. I-10 westbound traffic will detour to the Washington exit to Old Katy Road to the I-10 westbound frontage road and re-enter the I-10 mainlanes after Antoine.

. There will be a TOTAL CLOSURE of the I-10/KATY FREEWAY westbound direct connector ramp to I-610/WEST LOOP north- and southbound beginning 9 PM, Friday, February 1 until 5 AM, Monday, February 4. I-10 westbound traffic destined to I-610 northbound will detour to Old Katy Road, to the I-610 northbound frontage road. I-10 westbound traffic destined to I-610 southbound will detour to Old Katy Road, make a left on North Post Oak to access the I-610 southbound frontage road and enter the I-610 mainlanes after Woodway.

Please note that all closures are subject to change in the event of inclement weather. For more information on the Katy Freeway Reconstruction Program including up to date information regarding other lane closures along the I-10 corridor, please visit the Katy Freeway website at www.katyfreeway.org or contact the Katy Freeway Public Information Office at 281-589-5924.


Powered by NewsRouter.com

[Katy Freeway] [] [Program Overview] [Program Timeline] [Newsroom] [Lane Closures] [FAQs] [Feedback] [Sitemap]

Image: TxDOT Logo and Copyright 2000